Wall Street Neighborhood Project

The Wall Street Neighborhood Project is primarily a project to increase drainage in the neighborhood. The Project is being funded by FEMA, CDBG-DR, and the City. 

Wall Street will be entirely repaved, while the other streets will be partially repaved. You can see a map of exactly where the construction will take place by clicking here. All storm sewer lines will be replaced. Water and sewer lines are not under the streets and are not a part of this project. They will be completed at a later date. 

General Construction Schedule

This is the time line for likely construction, but it is subject to change:

  • Wall Street 4/21/21 – 8/4/21
  • Crawford St 7/29/21 – 9/30/21
  • Carlsbad St 8/20/21 – 12/1/21
  • Tahoe St 9/10/21 – 12/28/21
  • Capri St 9/19/21 – 1/31/22
  • Pump Station 6/1/21 – 8/1/21
  • Cleanup February 2022

Construction Updates

Construction updates will be posted no earlier than Thursday afternoons.  Please scroll down for earlier project updates. 

The week of May 10 the contractor is scheduled install more RCB's along wall street and a 30" storm water pipe along Wall Street.

The week of May 3 the contractor continues to install Reinforced Concrete Boxes (RCB) along Wall Street. The city received a traffic control plan, and has reviewed that. This should help improve some of the traffic flow issues. Uniform curb drains will be installed as part of the project. 

The week of April 26 they will continue construction of junction boxes. Please use caution when driving on Wall Street. 

The week of April 18 they began construction on the junction boxes in preparation of connecting into the existing storm sewer. 

The week of April 12 the contractor will mobilize to the site, start traffic control, tree protection, and SWPPP. They are scheduled to begin digging and construction during on April 21, 2021.